Date : 25/02/2016
During the first week, we discussed the various proposed projects. Each members of the team thought about his background and the link with all the projects. Next, everyone gave his opinion about each subject and his preference. Finally, we made a list with the three main topics taking into account the views of each. However, all the team agreed to put the Wooden Dome Shelter as first choice. A few days later, we knew that our topic for the semester would be our first choice. In this way, we started to collect informations about it and define our goal for the following months.
Date : 03/03/2016
Date : 10/03/2016
This week we worked on the planning and we defined and allocated the different tasks in the group. We also had some discussions about the function of the dome. In the end we decided that we are going to make it a weekend house. We also brainstormed with the supervisors about the connexion between the different beams and about the automatic door and windows. The rest of our time, we did research on the subject of domes.
Date : 17/03/2016
This week we focussed on our deadline to make the black box diagram and the structural drawings. We started to write the state of the art in the wiki.
Date : 31/03/2016
During these two weeks, we made the cardboard model and the system schematics. We also defined the structural drafts of the dome. We started the marketing plan, sustainability and project management report and we finished the state of the art. Furthermore, we created the flyer to sell our dome. On the function point, we came back on our decision. Finally, we prefered to sell the dome as a multifunctional place to touch more customers.
Date : 07/04/2016
During this week, we continued the marketing plan, sustainability and project management report and we update the weekly report. We added the pictures references. However we have some problems with the bibliography that we have to solve. Furthermore, we worked a lot on the list of materials to respect the deadline. Moreover, we improved the 3D of the dome in order to do the right calculations.
Date : 14/04/2016
During this week, we finished the list of materials with providers and price. We started the Ethical and Deontological Concerns part. We also continued the marketing plan, sustainability and project management report. We worked on the windows and door design according to the advice from our supervisor. We tried to solve the problems with the bibliography but without success.
Date : 21/04/2016
This week was particularly busy. We worked a lot on the report trying to apply teachers advice. Furthermore, we tried to improve the design of the dome thanks to a 3D model. We designed the door in the shaped of “flower” and the windows. We started the strength calculations and we also defined the constructional and electronical components. We have still problems with bibliography, so we have to find a solution for this problem. Now, we have to define the functionnal tests and change the report with the supervisors advice given during the presentation.
Date : 12/05/2016
We were working especially in the materials of dome. Finishing the list of materials, looking on local suppliers and making a good budget. Our project is endorsed with 100€ and the budget is inside of this range, it was a great news for start to buy the materials. Besides, the group were working with the material of the panels, making a comparison about it and concluding with the use of plywood, since it is the best performance gives price quality.
Date : 19/05/2016
In the first meeting, the teachers explained us the different topics we can choose for our project. We had the opportunity to meet all the supervisors. Next, they presented us the various tools we have to use during the semester like the Wiki or the Google Calendar.
During the second meeting, we precised our objectives and expectations. You looked for more information about the project. Furthermore, our supervisors clarified some points of the topic and they gave us advice and more details about the dome structure, materials, fixation…
- Questions about the project :
We decided the function for our dome. It will be a weekend house. We also got more information about the testing and the models we have to build. We decided about how we are going to construct the door and the automatic windows.
- Questions about the project :
The supervisors told us to put more things in the wiki and explained us how to use the references. We talked about the connections of the beam.
- Questions about the project :
During this meeting, the supervisors gave us some advice about the system schematics and the structural drawing. We have to do a comparative study of the elements that we will use. Furthermore, we have to add some requirements in connection with the use cases and the functionnal tests.
- Questions about the project :
Add error free BibTeX references to the refnotes bib file.The supervisors gave us some advices about the design of the door and windows and asked us to correct some details in the list of materials such as space between number and unity or add the degree symbol. Furthermore, we have to choose only one power supply
- Questions about the project :
The supervisors said us that we can exceed the budget of € 4.51. However, we can't use an Arduino from the school. Furthermore, they gave us some advice about the presentation and the report. They also explained us how to fix correctly the references.
- Questions about the project :
Discussion about prototype and agreement about it. We decided to build a fourth part of dome with automatic door and window incorporated.
- Questions about the project :
List of materials was correct and we proceed to buy the materials.
Waiting for get the materials and start to work with the dome. For this reason we didn't have any question.
- Aluminium sheet
- Questions about the project :
This meeting we received more information about the deliverables. The aluminium sheet can not be payed with the money of ISEP because we didn't have an invoice dated before the purchase.